PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 88 Topic 9 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 88 Topic 9 Discussion

PMI-100 Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?


A.

Organizational process updates


B.

Quality metrics


C.

Change requests


D.

Quality control measurements