PMI-100 Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:


A.

Analysis


B.

Appetite


C.

Tolerance


D.

Response