PMI-100 Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

Analytical techniques are a tool and technique of which process in Project Procurement Management?


A.

Plan Procurement Management


B.

Control Procurements


C.

Conduct Procurements


D.

Close Procurements