PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 44 Topic 5 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 44 Topic 5 Discussion

PMI-100 Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

The following chart contains information about the tasks in a project.

PMI-100 Question 44

Based on the chart, what is the cost variance (CV) for Task 6?


A.

-2,000


B.

0


C.

1,000


D.

2,000