PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 36 Topic 4 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 36 Topic 4 Discussion

PMI-100 Exam Topic 4 Question 36 Discussion:
Question #: 36
Topic #: 4

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?


A.

Applying calendars


B.

Resource leveling


C.

Resource planning


D.

Resource conflict management


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.