PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 211 Topic 22 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 211 Topic 22 Discussion

PMI-100 Exam Topic 22 Question 211 Discussion:
Question #: 211
Topic #: 22

The Human Resource Management processes are:


A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.


B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.


C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.


D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.