Question #: 193
Topic #: 20

Which action should a project manager take to ensure that the project management plan is effective and current?


A.

Conduct periodic project performance reviews.


B.

Identify quality project standards.


C.

Follow ISO 9000 quality standards.


D.

Complete the quality control checklist.