PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 131 Topic 14 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 131 Topic 14 Discussion

PMI-100 Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

The probability and impact matrix is primarily used to:


A.

Quantify risk issues for trends during a quality audit.


B.

Develop a risk register for risk planning.


C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.


D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.