PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 119 Topic 12 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 119 Topic 12 Discussion

PMI-100 Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?


A.

Identify Risks


B.

Control Risks


C.

Plan Risk Management


D.

Plan Risk Responses