Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?


A.

Risk and uncertainty increase; the cost of changes increases.


B.

Risk and uncertainty increase; the cost of changes decreases,


C.

Risk and uncertainty decrease; the cost of changes increases.


D.

Risk and uncertainty decrease; the cost of changes decreases.