PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 101 Topic 11 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 101 Topic 11 Discussion

PMI-100 Exam Topic 11 Question 101 Discussion:
Question #: 101
Topic #: 11

When should quality planning be performed?


A.

While developing the project charter


B.

In parallel with the other planning processes


C.

As part of a detailed risk analysis


D.

As a separate step from the other planning processes