Question #: 8
Topic #: 1

A method to manage stakeholder expectations in the scope statement is to clearly:


A.

state the guiding principles of the organization.


B.

identify alternatives to generate different approaches.


C.

state what is out of scope.


D.

outline the results of the Delphi technique.