PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 1 Topic 1 Discussion

PMI Certified Associate in Project Management (CAPM)® PMI-100 Question # 1 Topic 1 Discussion

PMI-100 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?


A.

Project sponsor


B.

Project manager


C.

Person responsible for project scheduling


D.

Person who is most familiar with the task


Get Premium PMI-100 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.