PMI Program Management Professional (PgMP) PgMP Question # 92 Topic 8 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 92 Topic 8 Discussion

PgMP Exam Topic 8 Question 92 Discussion:
Question #: 92
Topic #: 8

There are five stages of team development. At which stage are there likely to be disagreements and struggle for roles in the program team?


A.

Adjourning


B.

Forming


C.

Confronting


D.

Storming