Question #: 148
Topic #: 13

You are the program manager for your organization and are working with your program team to create the

program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?


A.

Phase gate estimates


B.

Murder board


C.

Portfolio review sessions


D.

Kill points