PMI Program Management Professional (PgMP) PgMP Question # 130 Topic 11 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 130 Topic 11 Discussion

PgMP Exam Topic 11 Question 130 Discussion:
Question #: 130
Topic #: 11

You are the program manager for your organization and you're trying to determine if you buy or build a software solution for your organization. If you build the solution it'll cost you $75,000 to create and it'll cost you

$12,000 per month to support. If you hire a vendor they can build the solution for $63,000 but their solution will cost you $15,500 per month to support. How many months would you have to use your in-house solution to equate to the cost of the vendor's solution?


A.

Approximately 6 months


B.

You'll never be able to equate to the cost of the vendor's solution.


C.

Approximately 3.5 months


D.

Approximately 10 months


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.