PMI Program Management Professional (PgMP) PgMP Question # 122 Topic 11 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 122 Topic 11 Discussion

PgMP Exam Topic 11 Question 122 Discussion:
Question #: 122
Topic #: 11

Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?


A.

Incorporate it into the risk register and perform a thorough analysis.


B.

Mitigate the risk before it is incorporated into the risk management plan.


C.

Document the risk in the program transition plan and identify it as a potential issue.


D.

Document it in the issue log and immediately notify the steering committee.