PMI Program Management Professional (PgMP) PgMP Question # 31 Topic 1 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 31 Topic 1 Discussion

PgMP Exam Topic 1 Question 31 Discussion:
Question #: 31
Topic #: 1

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?


A.

Negative ten percent B. .75


B.

$300,000 D. $225,000


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.