PMI Program Management Professional (PgMP) PgMP Question # 27 Topic 1 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 27 Topic 1 Discussion

PgMP Exam Topic 1 Question 27 Discussion:
Question #: 27
Topic #: 1

Andy is the program manager of the HQN Program. This program is nearing its completion and there is still

$25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?


A.

Value-added change requests


B.

Zero based budgeting


C.

Integrated change control


D.

Gold plating