PfMP Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

As a result of optimization, one of the components was deemed necessary to be terminated. One of the executive managers found about this and called you telling you that you should leave this component as it is of interest to her and she wants to see it finalized and that she will make resources available to it if needed. What should be your best course of action?


A.

Ask the steering committee for more resources in order to be able to continue with this component


B.

Ask the senior manager directly for resources as you know that this component requires additional resources


C.

Highlight the issue in the governance board meeting and recommend termination based on facts and thorough analysis


D.

Continue working on the component as you have the support of one of the senior managers