PfMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

Processes in the portfolio management layer interact with each others. For example, Manage Portfolio Information interacts with Provide Portfolio Oversight in order to store decisions made during the portfolio review meetings. Where are these decisions stored?


A.

Portfolio Management Plan


B.

Portfolio


C.

Portfolio Reports


D.

Portfolio Process Assets