PMI Portfolio Management Professional (PfMP) PfMP Question # 51 Topic 6 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 51 Topic 6 Discussion

PfMP Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

An organization decided to increase its business by 80% and approach new different clients. This strategy is followed because previously this organization was depending with its sales on only one client. With this new approach, you can describe the organization as being


A.

Pessimistic


B.

Risk Averse


C.

Risk Taker


D.

Optimistic