Question #: 43
Topic #: 5

Developing the Portfolio Management Plan is a major step in a Portfolio and for a Portfolio Manager. You are currently developing this plan and having focus groups and brainstorming activities during which you are using mind-maps diagrams to organize the idea into logical groupings. Which of the below are you using?


A.

Integration Of Portfolio Management Plans


B.

Facilitation Technique


C.

Collaboration Technique


D.

Survey Technique