PMI Portfolio Management Professional (PfMP) PfMP Question # 33 Topic 4 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 33 Topic 4 Discussion

PfMP Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

After the second shutdown of the Government, your Agency Administrator realized that some essential programs had to continue even during the shutdown, some existing work along with some programs and projects in the pipeline perhaps were not needed, and resources may require reallocation. This example shows the:


A.

Need to reconsider portfolio selection criteria


B.

Need to revise the portfolio mix


C.

Importance of regular reviews by the Portfolio Review Committee


D.

Need to reevaluate the entire portfolio management cycle