PfMP Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

One of the junior portfolio managers learned that she needs to use the roadmap as an input to the portfolio management plan development. She does not understand why, and she came to you for advice. What is your advice to her?


A.

Roadmap contains the portfolio structure which is used to structure the components for management through the portfolio management plan


B.

Roadmap is not an input to this process


C.

Roadmap provides the prioritization model to the portfolio management plan


D.

High-level timelines in roadmap are used to define low-level schedule and timelines for portfolio components