PMI Portfolio Management Professional (PfMP) PfMP Question # 21 Topic 3 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 21 Topic 3 Discussion

PfMP Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

The portfolio manager defines the portfolio based on a listing of already existing work in the organization and selects the right components in order to be able to prioritize them. What do you use for defining the portfolio based on the listing of work?


A.

Prioritization


B.

Inventory of Work


C.

Portfolio Component Inventory


D.

Elicitation technique