PMI Portfolio Management Professional (PfMP) PfMP Question # 146 Topic 15 Discussion

PMI Portfolio Management Professional (PfMP) PfMP Question # 146 Topic 15 Discussion

PfMP Exam Topic 15 Question 146 Discussion:
Question #: 146
Topic #: 15

As you are the portfolio manager for your state government agency, which is undergoing a series of budget cuts, you are focusing attention on managing risks to the portfolio as the budget is reduced. You realize in this process the time and budget for risk management also will be reduced; these data are in the:


A.

Portfolio performance plan


B.

Portfolio strategic plan


C.

Portfolio management plan


D.

Portfolio financial plan


Get Premium PfMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.