PfMP Exam Topic 15 Question 142 Discussion:
Question #: 142
Topic #: 15

One of the stakeholders of one of your components came to you complaining that his manager is not receiving specific information on multiple components progress. What is your best course of action?


A.

Raise the issue to the governance board as you have already analyzed this manager


B.

Send the manager the needed information asked by the stakeholder


C.

Meet the manager and understand what information is required


D.

Add the manager to the weekly reports distribution list where there is a lot of information on the components