Question #: 109
Topic #: 11

You are managing a portfolio linked to multiple business units and you set clear accountabilities from the beginning to avoid delays and to enhance the decision making process. Roles and Responsibilities are recorded in multiple portfolio documents. Where are the portfolio component managers roles and responsibilities stored?


A.

Specifically the Communication Management Plan


B.

Strategic Plan


C.

Portfolio Management Plan


D.

Portfolio Process Assets