New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Disciplined Agile Senior Scrum Master (DASSM) Exam DASSM Question # 38 Topic 4 Discussion

PMI Disciplined Agile Senior Scrum Master (DASSM) Exam DASSM Question # 38 Topic 4 Discussion

DASSM Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

Which of these tools or techniques should be used to sequence work to deliver value quickly?


A.

Planning Poker


B.

Minimum business increment (MBI)


C.

Work in process (WIP) limits


D.

Minimum viable product (MVP)


Get Premium DASSM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.