PMI Disciplined Agile Senior Scrum Master (DASSM) Exam DASSM Question # 26 Topic 3 Discussion

PMI Disciplined Agile Senior Scrum Master (DASSM) Exam DASSM Question # 26 Topic 3 Discussion

DASSM Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

The primary advantage of breaking a project into phases is that:


A.

It makes the transition from waterfall to agile easier


B.

You can bring in new teams in each phase depending upon the skills needed for it


C.

It allows the team to perform mini-waterfalls in each phase


D.

It enables teams to focus on critical themes and ease of governance