Disciplined Agile projects do not aim to maximize work-in-progress (WIP). Instead, they aim to minimize WIP to increase efficiency and reduce waste. By limiting WIP, teams can focus on completing tasks faster and delivering value more frequently. This approach is aligned with lean principles, which discourage multitasking and encourage teams to complete work items before starting new ones. Therefore, the statement that disciplined agile projects try to maximize WIP is false. The goal is to optimize the flow of work, not overload the team with too many concurrent tasks.
Top of Form
Bottom of Form
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit