Question #: 2
Topic #: 1

Why is the coordination meeting important for a project team?


A.

It provides a demo of the product to keep everyone up to date.


B.

It provides an opportunity for the team to help itself stay m sync.


C.

It allows the stakeholders to see how well the team is working together.


D.

If allows the team to reassess the backlog to meet their needs.