Question #: 4
Topic #: 1

You are leading a project to develop a new predictive maintenance solution. Together with your project team you determine your data needs, see if you have access to the data, and then begin working on the project.

Which phase best describes the work you are performing?


A.

Phase I


B.

Phase II


C.

Phase III


D.

Phase IV


E.

Phase V


F.

Phase VI