Question #: 2
Topic #: 1

Your organization has just rolled out a new image recognition system and is asking all employees to use it. It was trained using images from the ImageNet test set. After a few weeks, users are finding the results are not as expected and are asking for visibility into all the aspects of what went into building an AI system. What area of Trustworthy AI is being addressed here?


A.

Governed AI


B.

Transparent AI


C.

Explainable AI


D.

AI Systemic Transparency


E.

Responsible AI