The Benefits Map is typically created during the 'Defining a Programme' phase of the transformational flow. This map visually links programme outputs to expected benefits and outcomes, providing a clear picture of how the programme’s work will realize its intended value.
The MSP Practitioner explains:“Benefits are identified and analyzed in Defining a programme,”which highlights that the Benefits Map is a key planning tool used to understand dependencies, confirm benefit ownership, and ensure alignment with strategic objectives before detailed delivery begins.
Creating the Benefits Map at this stage supports informed decision-making and prioritization, as well as effective communication with stakeholders about how change initiatives contribute to strategic goals. It also serves as a baseline for benefits realization planning and tracking throughout programme delivery.
By defining and mapping benefits early, the programme can mitigate risks of misalignment or overlooked benefits, thereby improving chances of successful transformation and measurable value creation.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit