Oracle Cloud Infrastructure 2025Migration Architect Professional 1z0-1123-25 Question # 5 Topic 1 Discussion

Oracle Cloud Infrastructure 2025Migration Architect Professional 1z0-1123-25 Question # 5 Topic 1 Discussion

1z0-1123-25 Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

What is a valid purpose for creating multiple Migration Plans for each Migration Project in Oracle Cloud Migrations?


A.

To create a backup from the existing Migration Plan, as a precautionary measure against misconfiguration


B.

To validate different compute shapes for each VM ensuring the most effective configuration can be chosen


C.

To incrementally increase the allocated budget for each Migration Plan


D.

To accelerate the migration task by assigning each Migration Plan to the respective migration team