Question #: 11
Topic #: 2

Your client informs you that after running the " Process Item Structure Changes to Work Definitions " scheduled process, they received a workflow notification.

Which statement is NOT a workflow notification that you might get if automation is not performed?


A.

The replacement component has been assigned as an ad hoc Item to the same operation as the original component.


B.

The manufacturing plant Is enabled for ERES, the work definition changes are not expected to go through an approval process.


C.

The original component is not assigned to any work definition operation.


D.

The original component has been assigned to more than one work definition operation.