Your client is planning to override the Plant Production Calendar with One or More Date-Effective Work Center Calendars. You need to explain the consideration when using the Override the Plant Production Calendar with One or More Date-Effective Work Center Calendars feature.

Which three statements are true when overriding the production calendar?


A.

The Work Execution Work Area Infolets and Manage Production Exceptions page are based on the plant calendar and not on work center calendars.


B.

While defining override calendars, you need to ensure that the date effective range for a work center calendar association can be overlapping and contiguous.


C.

Even if there are override calendars, the lead time calculation in days for an item remains based on the plant calendar and not on work center calendars.


D.

When the user executes search action in the Review Dispatch List page, if more than one work center are selected and if the start date or completion date is based on Shift-based search, then the operations are queried based on the shifts of the plant calendar only.


E.

Supplier operations used in outside processing use the work center calendar in work order scheduling.