When pick release creates movement requests for project-based work orders, there are several key points regarding expenditure information:
Statement D:The expenditure type and the expenditure organization from the work order are not referenced onto the shop floor movement requests– This statement is correct because the expenditure type and organization are not typically included in the shop floor movement requests. These requests focus more on the material movement aspects, while expenditure details are managed elsewhere in the system.
[: Oracle Cost Management documentation clarifies that shop floor movement requests handle inventory and material flow, and expenditure information is derived later in the process, not directly tied to these requests., Incorrect Statements:, Statement A: The expenditure type, date, and organization are derived when interfacing with Costing, which ensures that project-related costs are tracked accurately., Statement B: The expenditure type for the item is derived based on the default expenditure type in Inventory Management, which is true for how items are picked for a work order., Statement C: Expenditure type and organization from the work order are referenced in costing, but not directly on movement requests., , ]
Submit