Oracle Planning and Collaboration Cloud 2024 Implementation Professional 1z0-1066-24 Question # 31 Topic 4 Discussion
1z0-1066-24 Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4
A supply plan has just been run that contains a configured item. You notice that the sourcing rules of the base model were used instead of sourcing rules for the configured item. Why did this happen?
A.
No sourcing rules have been defined for the configured item.
B.
The sourcing rules of the base model overrode the sourcing rules of the configured item.
C.
It is not possible to create sourcing rules for the configured item; all configured items always use the same sourcing rules as the base model.
D.
The sourcing rules of the base model had a priority of 1, while the sourcing rules of the configured item had a priority of 2.
E.
No planning percentages were defined at the operation level within the work definition.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.