Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 30 Topic 4 Discussion

Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 30 Topic 4 Discussion

1z0-1057-24 Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)


A.

If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.


B.

If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.


C.

If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.


D.

If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with thelowest number at the lowest level.