Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 22 Topic 3 Discussion

Oracle Project Management Cloud 2024 Implementation Professional 1z0-1057-24 Question # 22 Topic 3 Discussion

1z0-1057-24 Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.

What is the reason for this problem?


A.

Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.


B.

Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.


C.

You can enable automatic reprocessing of expenditure items processed before the burden schedule change.


D.

All expenditure items charged to the task use the new burden schedule.


Get Premium 1z0-1057-24 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.