OCEG GRC Professional Certification Exam GRCP Question # 28 Topic 1 Discussion

OCEG GRC Professional Certification Exam GRCP Question # 28 Topic 1 Discussion

GRCP Exam Topic 1 Question 28 Discussion:
Question #: 28
Topic #: 1

What is the term used to describe the level of risk in the absence of actions and controls?


A.

Uncontrolled Risk


B.

Inherent Risk


C.

Vulnerability


D.

Residual Risk