Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

OCEG GRC Professional Certification Exam GRCP Question # 28 Topic 1 Discussion

OCEG GRC Professional Certification Exam GRCP Question # 28 Topic 1 Discussion

GRCP Exam Topic 1 Question 28 Discussion:
Question #: 28
Topic #: 1

What is the term used to describe the level of risk in the absence of actions and controls?


A.

Uncontrolled Risk


B.

Inherent Risk


C.

Vulnerability


D.

Residual Risk


Get Premium GRCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.