A customer is testing a newly installed NetApp AFF A400 all-flash HA storage system. An SVM for FCP with a LUN on Node 1 has been configured, and a server has been connected as shown in the exhibit. For testing, the engineer plans to do a storage failover of Node 1.

After the failover, what is the expected status of the marked path?


A.

Unavailable


B.

Active/Optimized


C.

Active/Nonoptimized


D.

Offline