Which is included, as a minimum, in risk prioritization?


A.

Understanding the combined effect of risk to objectives when risks are viewed collectively


B.

Identifying uncertain events that could have an effect on the achievement of objectives


C.

Assessment of the risk profile of the programme in order to assess its viability


D.

Assessment of the likelihood of the risk occurring