You have been assigned as Test Analyst on a project that is in the test design stage. Test cases have been written, which activity should you do next before test design is complete?
A.
Identify constraints and dependencies that will affect the sequence of test execution
B.
Decide which test cases should be high-level and which ones should be low-level
C.
Identify the test cases that are suitable for automation
The test design activity develops test cases and defines relevant input, expected results and supporting requirements. Before the design is considered sufficiently complete, the quality of the test cases should be assessed through review. Stakeholders can confirm that the cases are understandable, precise, consistent, complete and aligned with the requirements and business objectives. Their input can reveal incorrect expected results, missing conditions and ambiguous terminology before test implementation and execution. Determining the required abstraction level normally occurs during design, prior to or alongside the derivation of the cases, rather than after all cases have been written. Scheduling execution and managing dependencies are particularly relevant during test implementation. Identifying candidates for automation can occur during planning or design, but does not replace the review of already designed cases. In the circumstances given, obtaining the appropriate stakeholder review is the strongest next activity, helping ensure that the testware is suitable before resources are committed to its implementation.
[Reference: CTAL-TA v4.0, Section 1.3.2 — Quality Criteria for Test Cases.]
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit