Question #: 32
Topic #: 4

MNO, Inc. hires a contractor to renovate its office space. The firm pays a deposit for new countertops for the office’s cafeteria, but the contractor states that it will not be able to install the new countertops by the agreed upon date. The space needs to be completed on time for a planned grand opening event. Which of the following is the BEST course of action for MNO to take?


A.

Withhold further payment to the contractor until the contractor makes arrangements to complete the contract as negotiated


B.

Seek remedy from the contractor for the uncompleted portion of the contract and award the remaining portion to another supplier


C.

Dismiss the contractor, request a refund of all deposits, and hire the second best contractor from the bid process


D.

Determine when the contractor can complete the cafeteria space, and schedule the event for one week later