Question #: 75
Topic #: 8

Which of the following is the FIRST step in the category management process?


A.

Conduct contract negotiations with strategic and/or preferred suppliers


B.

Develop a strategy to classify suppliers capable of providing material requirements


C.

Conduct market research to understand the supply market


D.

Build the team and project charter and develop a scope of work