CCBA Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?


A.

Concept modelling


B.

Requirements architecture


C.

Backlog management


D.

Balanced scorecard