IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 32 Topic 4 Discussion

IIBA Certification of Capability in Business Analysis (CCBA) CCBA Question # 32 Topic 4 Discussion

CCBA Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?


A.

Concept modelling


B.

Requirements architecture


C.

Backlog management


D.

Balanced scorecard


Get Premium CCBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.